Devon/Ontarioville Resurfacing Project

 

Project Location:Devon Ave. from the West Village limits to Ontarioville Rd.  Ontarioville Rd. from Devon Ave. to Lake St. 
Phase:Construction
Project Status:Under Construction
Bid Opening Date:August 5, 2022 at 12:00 PM 
Mandatory Pre Bid Meeting:No
Construction Start DateSpring 2023 
Construction Completion Date:June 1, 2023 
Contractor:J. A. Johnson Paving Company 
Construction Engineer:HR Green
Design Engineer:In-House
Awarded Construction Amount:$527,500.00
Adjusted Final Construction Amount :TBD
Funding Source(s):COVID Relief Funds

ifer Chandler says:OB


OBJECTIVE: 










To improve the condition of the roadway by means of resurfacing the asphalt pavement. 

DESCRIPTION: 

This project includes the mill and overlay of the specified sections Devon Ave. and Ontarioville Rd. pavements.  It also includes spot curb and gutter repairs, any necessary road subgrade patching, underground structure improvements/adjustments, curb ramp improvements to comply with current ADA requirements, and all necessary restoration work.