Resurfacing Project

Project Name:   2024 Resurfacing 
Project Location:   Various Locations
Phase:  Phase 1
Project Status:   Preparing Bid Documents
Bid Opening Date:   TBD
Mandatory Pre Bid Meeting:   TBD
Construction Start Date:   Summer 2024
Construction Completion Date:   Winter 2024 
Contractor:   TBD
Construction Engineer:   Staff
Design Engineer:   Staff
Awarded Construction Amount:   $2,591,000
Adjusted Final Construction Amount:   TBD
Funding Source(s):  Road & Bridge, MFT