| Project Location: | Various Streets |
| Phase: | Phase 1 |
| Project Status: | Awarded |
| Bid Opening Date: | April 2, 2024 |
| Mandatory Pre-Bid Meeting: | April 29, 2024 |
| Construction Start Date: | Summer 2024 |
| Construction Completion Date: | Fall 2024 |
| Contractor: | Builders Paving, Inc. |
| Construction Engineer: | Staff |
| Design Engineer: | Staff |
| Awarded Construction Amount: | 2,988,000.00 |
| Adjusted Final Construction Amount: | TBD |
| Funding Source(s): | Road & Bridge, MFT, Invest in Cook |
DESCRIPTION: Pavement resurfacing (e.g., Milling, Surface Course), Partial Depth Pavement Patching, Full Depth Pavement Patching, Spot Drainage Improvements (e.g., Inlet Adjustments, Reconstruction, Curb and Gutter Replacement), ADA Sidewalk Curb Ramps, Pavement Markings, and related work.